Why Data Centers Remind Us How Bad It Can Get: Who Pays for AI’s Power and Water?

By

· Founder, The Main Street CMO · Updated

By John Gormally, founder of The Main Street CMO · Tucson-area resident · U.S. Marine Corps veteran · 28 years in enterprise cybersecurity and technology marketing · Last updated November 11, 2026

Who pays for data centers? Too often, local residents do, through higher electric rates, strained water supplies and deals negotiated behind nondisclosure agreements. History shows where that leads. Fighting back isn’t about saying no to AI. It’s about making the companies that will profit from these facilities pay their full share.

I live in the Tucson area, and this region just got a crash course in how data center deals get made. Project Blue played out before I moved here, but I live with what it left behind. When I had my own chance to weigh in on future data centers, I voted no.

In 2025, people around Tucson learned that a massive data center called “Project Blue” was being planned for land near Houghton Road and Interstate 10. They also learned that Pima County’s procurement director had signed a nondisclosure agreement back in 2023. That NDA named Amazon Web Services as the company behind the project and kept its role secret for up to five years.

Five years. On a project that would draw on our power grid and sit in one of the driest regions in the country.

I’m not anti-technology. I spent 28 years in enterprise cybersecurity and tech sales with companies like Cisco, IBM and Symantec, I’ve written about AI for Security Boulevard, and I run my marketing firm with AI agents every day. I know what data centers make possible. But I also know how big deals get done, and the pattern we’re seeing now is one we’ve watched before. I use AI agents every day, too, and I wrote about the AI productivity paradox and what that speed does to my own thinking.

Who pays for data centers?

This is the question that matters most, and it’s the one that’s hardest to get a straight answer on.

A data center needs three things in huge quantities: land, electricity and, in many designs, water. Land gets bought. But electricity and water come through public systems built and paid for by everyone. When a single customer suddenly needs as much power as a city, someone has to pay for the new power plants, transmission lines and substations.

The fair answer is that the customer who causes the cost should pay for it. In practice, that often isn’t what happens.

Researchers at Harvard Law School’s Electricity Law Initiative studied this in their 2025 paper, “Extracting Profits from the Public: How Utility Ratepayers Are Paying for Big Tech’s Power.” Authors Eliza Martin and Ari Peskoe found dozens of data center contracts negotiated outside the normal rate-setting process. As they explained in a summary of the research, if a special contract rate falls below what it costs the utility to serve that customer, other ratepayers can be forced to cover the difference. And because those contracts are often treated as proprietary, the public frequently can’t see the terms.

In other words, the deal is private. The bill is public.

How data centers are raising power costs for everyone else

The clearest evidence comes from PJM, the grid operator that serves about 65 million people across 13 states and Washington, D.C.

PJM runs auctions to secure enough power capacity for future years. According to reporting by Fortune, the July 2026 auction for 2028-29 cleared at the maximum price allowed under the cap, and the grid still came up about 6.8 gigawatts short of what it needs for reliability. PJM’s own independent market monitor, Monitoring Analytics, found that about $6.3 billion of the $16.4 billion in capacity charges from that auction was directly attributable to data center demand. Across the last four auctions, data centers account for roughly $29.4 billion.

Those costs don’t stay at the wholesale level. They flow into the monthly bills of households and small businesses. Moody’s Ratings put it plainly in July 2026, as Fortune reported: the current system “lacks adequate mechanisms to ensure that the cost of building new supply is borne by the new entrants.”

That’s the heart of it. A family in Ohio or Maryland didn’t ask for an AI training cluster down the road. But they’re helping pay to power it.

Project Blue Tucson: what happened?

In Arizona, water is never a side issue. It’s the issue.

Public concern over Project Blue centered on how much water and energy the campus would use, especially given the early secrecy. After a crowd of roughly 1,000 people packed a community meeting at the Tucson Convention Center in August 2025, the Tucson City Council voted unanimously to end negotiations on Project Blue.

Then the project didn’t die. It changed shape. Developer Beale Infrastructure canceled its plans to expand Tucson’s reclaimed water system and promised an air-cooled design instead. In December 2025, the Pima County Board of Supervisors approved a binding agreement with Beale on a 3-2 vote. By that point, as one opponent noted, the developer didn’t even have an announced end customer.

To be fair, air cooling is a real improvement over evaporative cooling, and Beale committed to match its energy use with renewable power. That’s the kind of concession that only happens when people show up. But air cooling means more electricity. And that brings us back to who pays for the power.

The NDA problem: decisions made before you knew there was a decision

Project Blue isn’t unusual. NDAs have become standard practice in data center deals across the country.

An August 2026 investigation reported by NPR and its member stations found that in Rapides Parish, Louisiana, at least five state senators, the parish assessor and every member of a state-created development board signed NDAs about a $3.6 billion data center project that went by code names like “Project Lightning” and “Project Pixel.” Residents heard rumors for more than a year but were told the details were confidential. Records requests turned up at least 54 NDAs signed by Louisiana elected officials since early 2024.

It’s not just Louisiana. A University of Mary Washington study found NDAs in at least 25 of 31 Virginia data center projects it surveyed. The Minnesota Reformer documented the same pattern there.

Even the CEO of the company behind the Louisiana project admitted the problem. “It just feels sneaky to people,” he told reporters.

It feels sneaky because it is. When an elected official signs an NDA, the people they represent lose the chance to ask questions before the key decisions are made. By the time a project reaches a public vote, the land is optioned, the incentives are drafted and the momentum is enormous.

We’ve seen this movie before

None of this is new. Only the technology is new. The pattern of public resources going to private profit, often negotiated out of view, has played out again and again.

Foxconn in Wisconsin. In 2017, Wisconsin offered more than $3 billion in state tax incentives, plus nearly $1 billion more from local governments, for a Foxconn factory that was supposed to bring 13,000 jobs. As NPR reported, Foxconn missed the job targets needed to qualify for state money, and the factory came in at about 1 million square feet instead of the promised 22 million. Neighbors watched the land change while the jobs didn’t show up.

Nestlé in Michigan. While Flint residents waited for clean drinking water, Nestlé was pumping Michigan groundwater for bottled water and paying the state just $200 a year in paperwork fees. In 2018, the state approved its request to raise pumping to 400 gallons a minute, even though most public comments opposed it.

Amazon HQ2 in New York. New York offered almost $3 billion in state and city incentives for Amazon’s second headquarters, with a process that gave the City Council little say. When public pushback grew, Amazon walked away in February 2019.

Duke Energy. According to the Harvard researchers, a federal antitrust case revealed that Duke offered a large customer a contract worth a $325 million discount and planned to shift that cost to other ratepayers in the years to come.

The common thread: the company gets the benefit up front. The community gets the risk, the bill or both.

A global play with a local price tag

Here’s what bothers me most about the current wave of AI data centers. Most of them aren’t really about the town where they’re built.

A hyperscale AI campus serves customers worldwide. It trains models that will be sold globally. The profits flow to shareholders far from the county that hosts it. But the costs are stubbornly local: the substation upgrade, the new gas plant, the groundwater, the noise, the traffic during construction and the higher electric bill.

Look at Meta’s Hyperion campus in rural Richland Parish, Louisiana. According to Fortune, the project will now be supported by 10 gas-fired plants totaling 7.5 gigawatts, more than a 30% increase to Louisiana’s total grid capacity, at an estimated cost of nearly $11 billion. Meta says it’s covering the cost of the new plants. That’s good. But critics warn that ratepayers could be left holding the bill after the 15-year contract term if Meta’s power needs drop.

Or look at Memphis. The Southern Environmental Law Center reports that xAI installed 27 unpermitted gas turbines in Southaven, Mississippi, to power its Colossus 2 data center, without public input or notice to nearby neighborhoods. Those turbines could emit more than 1,700 tons of nitrogen oxides a year in an area that already fails national smog standards.

A global company. A global product. A local bill paid in dollars and in air quality.

Why fighting back isn’t saying no to AI

Let me be clear about where I stand. I use AI every day. I think it’s going to change how small businesses compete. I’m not asking anyone to stop building data centers.

I’m asking that the companies that profit from them pay what they cost.

That’s not radical. It’s how we expect every other business to operate. If I open a second office, I don’t get to send my electric bill to my neighbors.

And there’s proof that this approach works without killing growth:

  • Make them pay for the capacity they reserve. In July 2025, Ohio regulators approved AEP Ohio’s data center tariff, requiring new data centers over 25 megawatts to pay for at least 85% of the power capacity they sign up for, whether they use it or not, for up to 12 years, with exit fees if they leave early. Ohio didn’t ban data centers. It made sure they couldn’t walk away and leave everyone else with stranded costs.
  • End secret deals. Pima County adopted a “sunshine period” requiring companies to be named before any public vote. Pennsylvania’s governor banned NDAs for data center projects at agencies under his oversight, and bills to ban them have been introduced in Michigan, Oklahoma, Kentucky and Ohio.
  • Challenge rates set outside the rules. Arizona Attorney General Kris Mayes asked for a rehearing on the Tucson Electric Power agreement for Project Blue, arguing it let the utility and the customer set rates outside the approved tariff. Her warning: deals where a data center doesn’t pay its fair share “can result in the shifting” of costs to everyone else.
  • Require water disclosures up front. Marana now requires developers to estimate annual water use and identify the source. Tucson requires large water users to apply for service and show conservation efforts.
  • Prove it can be done in the open. West Feliciana Parish, Louisiana, landed a $10 billion data center without NDAs and posted the project documents online. Its parish president said deals “should be out in the open.”

Washington is starting to notice, too. In September 2026, the House passed the Ratepayer Protection Act, which would have states consider standards requiring large power users to pay for the grid upgrades they cause, though it stalled in the Senate. On October 14, Rep. Eugene Vindman introduced the Make Data Centers Pay Act, which would amend the Federal Power Act so data centers using 20 megawatts or more cover the full added cost of serving them instead of shifting it to households and small businesses.

What you can do

You don’t have to be an energy lawyer to make a difference. Here’s where ordinary people have moved the needle:

  1. Show up early. By the time a rezoning vote happens, the deal is mostly done. Attend planning and zoning meetings, not just the final council vote.
  2. Ask who the end customer is. If officials can’t or won’t say, ask why.
  3. File public records requests. That’s how Arizona Luminaria confirmed Amazon’s role in Project Blue.
  4. Follow your utility commission. Rate cases and special contracts are where the real money moves. In Arizona, that’s the Arizona Corporation Commission.
  5. Ask for guarantees in writing. Minimum-demand charges, exit fees, independent water audits and community benefit agreements beat verbal promises every time.

The bottom line

Data centers remind us how bad it can get when big money and public resources meet behind closed doors. We’ve seen it with factories that never filled, water that was sold for pennies and headquarters deals that bypassed the people paying for them.

But Project Blue also shows something else. When a thousand people showed up at the Tucson Convention Center, the conversation changed. The water plan changed. The county’s NDA rules changed.

AI is coming either way. The only question is who pays for it. The companies that will earn billions from these facilities can afford their own power, their own water and their own infrastructure. Our job is to make sure they do.

Say yes to the future. Just don’t sign the check for someone else’s profits.

Sources

Frequently asked questions

Who pays for data centers?

In theory, the data center company pays for the land, buildings and equipment. But the cost of new power plants, transmission lines and grid upgrades is often spread across all utility customers. Harvard researchers found that special contracts can shift these costs to households when the data center’s rate is below the cost to serve it.

Are data centers raising electric bills?

In some regions, yes. PJM’s independent market monitor found that data center demand accounted for about $6.3 billion of $16.4 billion in capacity charges from the July 2026 auction, costs that flow through to customer bills across 13 states and D.C.

Why do data centers use NDAs?

Companies say NDAs protect competitive and market-sensitive information. Critics say they keep residents in the dark until key decisions are made. Investigations have found NDAs in most Virginia data center projects surveyed and dozens signed by Louisiana officials.

What was Project Blue in Tucson?

Project Blue is a large data center campus proposed by Beale Infrastructure near Houghton Road and I-10. A 2023 county NDA named Amazon Web Services as the intended user. The Tucson City Council voted unanimously to end negotiations in August 2025, and Pima County approved a revised air-cooled plan in December 2025.

How can communities make data centers pay their fair share?

Communities can push for minimum-demand tariffs like Ohio’s, exit fees, bans on NDAs for public officials, required water-use disclosures and written community benefit agreements before any rezoning vote.

Are taxpayers paying for data centers?

Often, yes, in two ways. Local governments offer tax breaks and incentives to win projects, and utility customers can end up covering grid upgrades through their electric bills. In PJM’s 13-state region, data center demand accounts for roughly $29.4 billion in capacity costs across the last four auctions, costs that flow into household and small business bills.

Who makes money when data centers are built?

The tech companies that use the computing capacity, the developers that build the campuses and the utilities that earn a return on new power plants and transmission lines. The profits mostly flow to shareholders far from the host community, while the costs of power, water and grid upgrades stay local.

Why are people against data centers being built?

Most opposition centers on water use, higher electric bills, noise, air pollution from on-site gas turbines and secrecy. In Tucson, about 1,000 people packed a community meeting over Project Blue’s water and energy use after learning a county NDA had kept Amazon’s role hidden.

About John Gormally

John Gormally is the founder of The Main Street CMO and CycleWriter LLC. A U.S. Marine Corps veteran (1982 to 1988), he spent 28 years in enterprise cybersecurity and technology sales and marketing with companies including Cisco, Citrix, IBM and Symantec before moving into marketing full-time. He holds a B.S. in Marketing and an MBA, plus post-graduate certificates from MIT and Cornell. He has written about 800 blogs and articles, including bylines on Security Boulevard, is a member of the American Marketing Association, and writes award-winning military cyber-thrillers as Patrick Greenwood.

About The Main Street CMO

The Main Street CMO is a veteran-owned marketing firm in Oro Valley, Arizona, and a member of the Greater Oro Valley Chamber of Commerce. It provides fractional CMO services, SEO, answer engine optimization (AEO), generative engine optimization (GEO), content marketing and paid social for small businesses, MSPs, IT companies and cybersecurity firms.

Leave a Reply

About the Author

John Gormally is a U.S. Marine Corps veteran and the founder of The Main Street CMO, a small business marketing agency in Oro Valley, Arizona. He spent 28 years marketing technology for Cisco, Citrix, BlackBerry and IBM.

About John ↗